Work includes; construction of three water treatment buildings with Chlorination and testing facilities. construction of three new wells, jack hammering of casings under Highway No.1 and more than 1,500m of 200mm to 100mm diam watermains. Decommissioning of old well, construction of three two-room treatment buildings Construction of approx. 150m of access road and drainage work. Commissioning of new treatment buildings.